42 feet of floor to ceiling glass
       
     
DSC_8195.JPG
       
     
DSC_6508.JPG
       
     
DSC_8467.JPG
       
     
The foundation started 55 feet below the street. We repelled down each day to the work area.
       
     
DSC_7968.JPG
       
     
DSC_7970.JPG
       
     
Our design for the suspended pool deck added considerable extra space.
       
     
DSC_7971.JPG
       
     
The site required a temporary shoring wall to support the roadway and existing services.
       
     
Our design included 96 rock anchors drilled 15 feet into the rock. The home and pool would literally hang off the rock face should there be any unlikely movement of the lower material.
       
     
IMG-20141003-00014.jpg
       
     
P1020928.JPG
       
     
It took hours of planning to effectively co ordinate the tasks required on such a tight site.
       
     
P1020796.jpg
       
     
2 excavators, a rock drill, blasting mats and the building materials had to be exactly co ordinated to ensure efficiency.
       
     
 The foundation consisted of multiple pours. 55 vertical feet of concrete wall was required. 
       
     
DSC_7965.JPG
       
     
DSC_7963.JPG
       
     
 Pictured is a pneumatic rock drill we used for many precision blasts. The closest building is a mere 7 feet away from the property line. Many blasts were required and we completed the job with no damage and no injuries. There were no injuries d
       
     
DSC_7972.JPG
       
     
A 120 ton conventional crane was onsite for a year and lifted equipment up to 55,000 lbs.
       
     
P1070929.jpg
       
     
 Pictured is a 120 ton conventional crane we had onsite for a year. It lifted our 29000 lb machine with ease. Our largest lifts were with a 55000 lb excavator.
       
     
P1070911.jpg
       
     
P1050089.JPG
       
     
P1050090.jpg
       
     
Preparations for the hydronic heat on the 3rd floor down.
       
     
P1070916.JPG
       
     
P1070924.JPG
       
     
This home presents almost every challenge there is on a residential site.
       
     
P1070920.jpg
       
     
P1050092.JPG
       
     
P1050548.jpg
       
     
P1070928.JPG
       
     
DSC_7969.JPG
       
     
42 feet of floor to ceiling glass
       
     
42 feet of floor to ceiling glass
DSC_8195.JPG
       
     
DSC_6508.JPG
       
     
DSC_8467.JPG
       
     
The foundation started 55 feet below the street. We repelled down each day to the work area.
       
     
The foundation started 55 feet below the street. We repelled down each day to the work area.
DSC_7968.JPG
       
     
DSC_7970.JPG
       
     
Our design for the suspended pool deck added considerable extra space.
       
     
Our design for the suspended pool deck added considerable extra space.
DSC_7971.JPG
       
     
The site required a temporary shoring wall to support the roadway and existing services.
       
     
The site required a temporary shoring wall to support the roadway and existing services.
Our design included 96 rock anchors drilled 15 feet into the rock. The home and pool would literally hang off the rock face should there be any unlikely movement of the lower material.
       
     
Our design included 96 rock anchors drilled 15 feet into the rock. The home and pool would literally hang off the rock face should there be any unlikely movement of the lower material.
IMG-20141003-00014.jpg
       
     
P1020928.JPG
       
     
It took hours of planning to effectively co ordinate the tasks required on such a tight site.
       
     
It took hours of planning to effectively co ordinate the tasks required on such a tight site.
P1020796.jpg
       
     
2 excavators, a rock drill, blasting mats and the building materials had to be exactly co ordinated to ensure efficiency.
       
     
2 excavators, a rock drill, blasting mats and the building materials had to be exactly co ordinated to ensure efficiency.
 The foundation consisted of multiple pours. 55 vertical feet of concrete wall was required. 
       
     

The foundation consisted of multiple pours. 55 vertical feet of concrete wall was required. 

DSC_7965.JPG
       
     
DSC_7963.JPG
       
     
 Pictured is a pneumatic rock drill we used for many precision blasts. The closest building is a mere 7 feet away from the property line. Many blasts were required and we completed the job with no damage and no injuries. There were no injuries d
       
     

Pictured is a pneumatic rock drill we used for many precision blasts. The closest building is a mere 7 feet away from the property line. Many blasts were required and we completed the job with no damage and no injuries. There were no injuries during the entire process. Safety is something we take quite seriously. 

DSC_7972.JPG
       
     
A 120 ton conventional crane was onsite for a year and lifted equipment up to 55,000 lbs.
       
     
A 120 ton conventional crane was onsite for a year and lifted equipment up to 55,000 lbs.
P1070929.jpg
       
     
 Pictured is a 120 ton conventional crane we had onsite for a year. It lifted our 29000 lb machine with ease. Our largest lifts were with a 55000 lb excavator.
       
     

Pictured is a 120 ton conventional crane we had onsite for a year. It lifted our 29000 lb machine with ease. Our largest lifts were with a 55000 lb excavator.

P1070911.jpg
       
     
P1050089.JPG
       
     
P1050090.jpg
       
     
Preparations for the hydronic heat on the 3rd floor down.
       
     
Preparations for the hydronic heat on the 3rd floor down.
P1070916.JPG
       
     
P1070924.JPG
       
     
This home presents almost every challenge there is on a residential site.
       
     
This home presents almost every challenge there is on a residential site.
P1070920.jpg
       
     
P1050092.JPG
       
     
P1050548.jpg
       
     
P1070928.JPG
       
     
DSC_7969.JPG